HIGH BUILD SYSTEM
(Solid Color)
Click on photo to enlarge.
Installation Process:   


Click here to see the surface preparation process for residential projects.
Click here to see the surface preparation process for commercial/industrial projects.
First Coat:
• Apply deep penetrating epoxy primer to floor surfaces (175 to 200 sq. ft. per gal.)
• Allow primer to cure for about 1 to 24 hours
• Lightly sand (either mechanically or by hand) the floor to remove any foreign debris trapped in the drying process and smooth the surface (if necessary)

Second Coat:
• Apply a coat of 100% solids epoxy to floor surface (~ 100 sq. ft. per gal.)
• Allow epoxy coat to cure for about 24 hours
• Lightly sand (either mechanically or by hand) the floor to remove any foreign debris trapped in the drying process and smooth the surface (if necessary)

Third Coat, Finish:
• Apply a finish coat of UV resistant polyurethane with aluminum oxide (added for slip resistance) to floor surface (250 to 300 sq. ft. per gal.)