DECORATIVE QUARTZ
Click on images to enlarge
Installation Process:   


Click here to see the surface preparation process for residential projects.
Click here to see the surface preparation process for commercial/industrial projects.

Double Broadcast Decorative Quartz System (~ 3/32" to ~ 1/8”)


First Coat:
• Apply a clear binder coat of 100% solids epoxy to floor surface (~ 160 sq. ft. per gal.)
• While the binder coat is still wet, broadcast the colored quartz to rejection
• Allow epoxy coat to cure for about 24 hours
• Sweep off any loose quartz


Second Coat:
• Apply a clear binder coat of 100% solids epoxy to floor surface (~ 120 sq. ft. per gal.)
• While the binder coat is still wet, broadcast the colored quartz to rejection
• Allow epoxy coat to cure for about 24 hours
• Sweep off and vacuum any loose quartz


Third Coat:
• Apply a coat of UV resistant, 100% solids epoxy (80 to 120 sq. ft. per gal.) or high solids polyurethane (250 to 300 sq. ft. per gal.) to floor surface
• Allow to cure for about 24 hours
• Lightly sand (either mechanically or by hand) the floor to remove any foreign debris trapped in the drying process and smooth the surface (if necessary)


Fourth Coat (Optional to create a smoother profile):
• Apply a coat of UV resistant polyurethane with aluminum oxide (added for slip resistance) to floor surface


Single Broadcast Decorative Quartz System (~ 1/16”)


First Coat:
• Apply deep penetrating epoxy primer to floor surface (250 to 350 sq. ft. per gal.), primer color will be tinted to match the color tone of the quartz blend selected
• Allow primer to cure for about 1 to 24 hours
• Lightly sand (either mechanically or by hand) the floor to remove any foreign debris trapped in the drying process and smooth the surface (if necessary)


Second Coat:
• Apply a clear binder coat of 100% solids epoxy to floor surface (~ 160 sq. ft. per gal.)
• While the binder coat is still wet, broadcast the colored quartz to rejection
• Allow to cure for about 24 hours
• Sweep off and vacuum any loose quartz


Third Coat:
• Apply a coat of UV resistant, 100% solids epoxy (80 to 120 sq. ft. per gal.) or high solids polyurethane (250 to 300 sq. ft. per gal.) to floor surface
• Allow to cure for about 24 hours


Fourth Coat (Optional to create smoother profile):
• Apply a coat of UV resistant polyurethane with aluminum oxide (added for slip resistance) to floor surface (250 to 300 sq. ft. per gal.)


Ervin Specialty Coatings  |  Cottonwood, AZ  |  (928) 649-9338  | ROC218645  ROC220641